Navy Ships - Problems Continue to Plague the Seawolf Submarine Program: Nsiad-93-171 (Paperback)


GAO reviewed the Navy's Seawolf (SSN-21) Class Nuclear-Powered Attack Submarine construction program, focusing on: (1) the change in the status of the class design and SSN-21 construction since December 1991; (2) the effectiveness of technical and management actions to resolve lead submarine welding problems and guard against a recurrence of a similar problem in the future; and (3) Navy efforts to control schedule delays. GAO found that: (1) SSN-21 construction has fallen at least 5 months behind schedule; (2) factors contributing to construction delays include late drawings and other design data, insufficient staff and problems preparing and releasing the instructions and materials needed for construction, and a smaller-than-expected SSN-21 construction work force; (3) 5 percent of the work packages scheduled for completion and 9 percent of the completed work packages scheduled for release to construction workers were delinquent; (4) the incompatibility between the design and construction schedules could further delay SSN-21 delivery; (5) it will cost $683 million to design the SSN-21 class, which is 125 percent over the original contract cost estimate; (6) cost increases are primarily due to changes in specifications, reductions in the number of submarines to be constructed, and the re-estimation of construction elements; and (7) the contractor has corrected the welding problems and instituted new welding procedures to prevent any recurrence of similar problems.

R325
List Price R406
Save R81 20%

Or split into 4x interest-free payments of 25% on orders over R50
Learn more

Discovery Miles3250
Delivery AdviceOut of stock

Toggle WishListAdd to wish list
Review this Item

Product Description

GAO reviewed the Navy's Seawolf (SSN-21) Class Nuclear-Powered Attack Submarine construction program, focusing on: (1) the change in the status of the class design and SSN-21 construction since December 1991; (2) the effectiveness of technical and management actions to resolve lead submarine welding problems and guard against a recurrence of a similar problem in the future; and (3) Navy efforts to control schedule delays. GAO found that: (1) SSN-21 construction has fallen at least 5 months behind schedule; (2) factors contributing to construction delays include late drawings and other design data, insufficient staff and problems preparing and releasing the instructions and materials needed for construction, and a smaller-than-expected SSN-21 construction work force; (3) 5 percent of the work packages scheduled for completion and 9 percent of the completed work packages scheduled for release to construction workers were delinquent; (4) the incompatibility between the design and construction schedules could further delay SSN-21 delivery; (5) it will cost $683 million to design the SSN-21 class, which is 125 percent over the original contract cost estimate; (6) cost increases are primarily due to changes in specifications, reductions in the number of submarines to be constructed, and the re-estimation of construction elements; and (7) the contractor has corrected the welding problems and instituted new welding procedures to prevent any recurrence of similar problems.

Customer Reviews

No reviews or ratings yet - be the first to create one!

Product Details

General

Imprint

Bibliogov

Country of origin

United States

Release date

May 2013

Availability

Supplier out of stock. If you add this item to your wish list we will let you know when it becomes available.

First published

May 2013

Creators

,

Dimensions

246 x 189 x 3mm (L x W x T)

Format

Paperback - Trade

Pages

52

ISBN-13

978-1-287-17623-7

Barcode

9781287176237

Categories

LSN

1-287-17623-2



Trending On Loot